It was good to see some old faces from last season in to help during the week

Progress in Week One
First main entrance stairs scrubbed down painted and ready for the new season.
Prep work on main stand railing fully de-rusted and first coat primer
applied.
Home end main stand final paint coat applied.

It was good to see some old faces from last season in to help during the week they enjoyed themselves with the banter.

Warning due to circumstances work for next week will only take place on Tuesday 31 May but normal days of Tuesday Wednesday Thursday will continue the following week.

Contact Dave Blackburn E mail chippyblackie@yahoo.co.uk tel
07506200846



Views : 4,936

Related Stories


Recent Stories
    Hot Stories
      • /files/business_clubadvert_3633.jpg
      • /files/KiltCompany_280_2285.jpg
      • files/Newsletter_advert_9112.jpg
      • files/CB_Dunfermline_Programme_Ad_300px_v2_9109.jpg
      Archives
      2024
      2023
      2022
      2021
      2020
      2019
      2018
      2017
      2016
      2015
      2014
      2013
      2012
      2011
      2010
      2009
      2008
      2007
      2006
      2005
      2004
      2003
      2002
      2001
      2000
      1999
      1998
      1997
      1996
      1995
      1991
      1986
      1979
      1968
      1965
      1962
      1961
      1960
      1957
      1949

      To top